Liquidated Damages Clauses in Oklahoma

A liquidated damages clause sets, in advance, the amount one party will pay if it breaches. These clauses appear in construction contracts, real estate earnest money provisions, leases, NDAs and service agreements. Oklahoma starts from skepticism: a pre-set damages figure is void unless it fits a narrow statutory exception. Bennett Vernier, PLLC drafts these clauses so they hold up and challenges clauses that function as penalties, as part of our business law and breach of contract practice.

Oklahoma's Starting Point: Penalties Are Void

Except as expressly provided in 15 O.S. § 215, penalties imposed by contract for non-performance are void (15 O.S. § 213). Every contract that fixes in advance the damages for a breach is void to that extent, except as § 215 allows (15 O.S. § 214).

The Exception for True Liquidated Damages

Outside real estate sales, a clause providing an amount presumed to be the damage from a breach is valid when, from the nature of the case, it would be impracticable or extremely difficult to fix the actual damage (15 O.S. § 215(A)). The Oklahoma Supreme Court has identified three criteria that separate valid liquidated damages from a penalty: (1) the injury caused by the breach must be difficult or impossible to estimate accurately; (2) the parties must intend to provide for damages rather than a penalty; and (3) the sum must be a reasonable pre-breach estimate of the probable loss (Sun Ridge Investors, Ltd. v. Parker, 1998 OK 22, ¶ 8, 956 P.2d 876). Whether actual damages can be fixed with reasonable accuracy is a question of law for the court (id. ¶ 12).

Real Estate Earnest Money: The Five Percent Rule

For real estate sales contracts, a liquidated damages provision is valid and not a penalty when the amount does not exceed five percent of the purchase price (15 O.S. § 215(B)). If the amount exceeds five percent, the provision is treated as a penalty unless the party seeking to uphold it proves the amount is reasonable. When the clause is valid, the usual measure of a seller's damages under 23 O.S. § 28 does not apply.

Late Fees and Daily Charges

Late fees are a frequent battleground. In Sun Ridge, the Supreme Court held that an apartment landlord's $5 per day late charge, on top of a $20 late fee, was an unenforceable penalty because the landlord offered no evidence of actual costs and its damages from late rent were not so difficult to determine. Businesses that rely on daily delay charges or per-breach amounts should be ready to show why actual damages were hard to measure and how the number was chosen.

Drafting a Clause That Holds Up

  • Explain in the contract why actual damages would be hard to calculate

  • Tie the amount to a realistic estimate made at signing, and keep the backup

  • Avoid labels like penalty and avoid amounts far beyond any plausible loss

  • Say whether the amount is the exclusive remedy or an alternative

  • For real estate, keep earnest money at or below five percent of the price, or document why a larger amount is reasonable

If You Are Facing a Liquidated Damages Claim

We look at whether the actual loss was easy to measure, whether the amount bears a reasonable relationship to it, and whether the other side's own conduct contributed to the delay or breach. If the clause fails, the claim falls back to ordinary contract damages under 23 O.S. § 21, which the claimant must prove. See also specific performance for cases where money is not the right answer. Call (405) 346-9800 or contact us online. We represent businesses and individuals across the Oklahoma City metro from our office at 6116 NW 63rd Street in Warr Acres.

Frequently Asked Questions

Are liquidated damages enforceable in Oklahoma?

Only when actual damages would be impracticable or extremely difficult to fix (15 O.S. § 215(A)) and the amount is a reasonable pre-breach estimate rather than a penalty (Sun Ridge Investors, Ltd. v. Parker, 1998 OK 22).

How much earnest money can a seller keep?

A real estate liquidated damages amount up to five percent of the purchase price is valid. Above five percent it is treated as a penalty unless the seller proves it is reasonable (15 O.S. § 215(B)).

Is a late fee a penalty?

It can be. In Sun Ridge, a $5 per day late charge on rent was held to be a penalty because the landlord did not show actual costs and the damages were not hard to determine.

What happens if a liquidated damages clause is struck down?

The injured party can still recover its actual damages under 23 O.S. § 21, but it must prove them.

Who decides whether a clause is a penalty?

The court. Whether actual damages can be fixed with reasonable accuracy is a question of law (Sun Ridge, ¶ 12).

This page is general information, not legal advice, and reading it does not create an attorney-client relationship. Every situation is different.