Mechanics' and Materialmen's Lien Attorney in Oklahoma

Oklahoma's mechanics' and materialmen's lien statutes give contractors, subcontractors, suppliers and equipment lessors security in the property they improved. They also impose short deadlines and technical requirements that defeat many liens. Bennett Vernier, PLLC files and forecloses liens for claimants and defends owners and lenders against improper liens. This page is part of our property law and breach of contract practice.

Who Can Claim a Lien

A person who, under an oral or written contract with the owner, performs labor, furnishes material or rents equipment used on the land for the erection, alteration or repair of a building, improvement or structure has a lien on the land, buildings and appurtenances for all sums owed, including applicable profit and overhead (42 O.S. § 141). Subcontractors, their laborers and suppliers may obtain a lien in the same manner (42 O.S. § 143).

Filing Deadlines

  • Original contractors: file a verified lien statement with the county clerk within four months after material or equipment was last furnished or labor last performed (42 O.S. § 142)

  • Subcontractors and suppliers to them: file within 90 days after the last furnishing or labor (42 O.S. § 143)

  • Pre-lien notice: claimants other than the original contractor generally must send a pre-lien notice to the original contractor and an owner no later than 75 days after the last furnishing, with exceptions for certain non-owner-occupied residential projects and aggregate claims under $10,000 (42 O.S. § 142.6)

  • Owner-occupied homes: no subcontractor or supplier lien on property then occupied as a dwelling by an owner is valid unless the pre-lien notice was sent within 75 days (42 O.S. § 142.6(B)(1))

  • Foreclosure: the lien must be enforced by a civil action filed within one year after the lien is filed (42 O.S. § 172)

After a lien is filed, the county clerk mails notice of it to the owner, and the claimant must supply the addresses (42 O.S. § 143.1). The claimant also files an affidavit verifying compliance with pre-lien notice requirements (42 O.S. § 142.6(C)).

Priority

A properly perfected lien is preferred to liens and encumbrances that attach after the work or materials began, and compliance with the statutes gives constructive notice to later purchasers and lenders from the date the first labor or material was furnished (42 O.S. § 141). Priority fights with construction lenders are common on commercial projects.

Protections for Owners

An owner is not liable to lien claimants for more than the owner contracted to pay the original contractor, and the owner may pay a subcontractor directly with credit against the contract price (42 O.S. § 143). Any interested party may discharge a lien by depositing cash or a surety bond equal to 125 percent of the claim with the county clerk, which moves the claim to the deposit or bond (42 O.S. § 147.1). This is useful when a sale or refinance cannot wait.

Attorney Fees

In an action to enforce a lien, the party for whom judgment is rendered recovers a reasonable attorney fee fixed by the court (42 O.S. § 176). That cuts both ways, so a weak lien can become expensive for the claimant.

How We Help

For contractors and suppliers, we calendar deadlines, prepare pre-lien notices and lien statements, and file foreclosure suits. For owners and lenders, we review liens for missed deadlines, defective notices and inflated amounts, bond off liens, and defend foreclosure actions. Homeowners dealing with a contractor who took payment and left should also read our page on home repair fraud. Expired or invalid liens that a claimant will not release can be cleared through a quiet title action. Call (405) 346-9800 or contact us online. We help property owners, buyers, sellers and lenders across the Oklahoma City metro from our office at 6116 NW 63rd Street in Warr Acres.

Frequently Asked Questions

How long does a contractor have to file a mechanics' lien in Oklahoma?

An original contractor has four months after the last labor or materials (42 O.S. § 142). Subcontractors and their suppliers have 90 days (42 O.S. § 143).

What is a pre-lien notice?

A written notice that most claimants other than the original contractor must send to the original contractor and an owner within 75 days after the last furnishing (42 O.S. § 142.6). It is mandatory for liens on owner-occupied homes.

How long does a lien last?

A lien must be enforced by a lawsuit filed within one year after it is filed with the county clerk (42 O.S. § 172).

How do I remove a lien so I can sell or refinance?

Any interested party may discharge it by depositing cash or a surety bond equal to 125 percent of the claim with the county clerk (42 O.S. § 147.1).

Who pays attorney fees in a lien case?

The party for whom judgment is rendered recovers a reasonable attorney fee (42 O.S. § 176).

This page is general information, not legal advice, and reading it does not create an attorney-client relationship. Every situation is different.